About Homer
-
- Americans with Disabilities Act Compliance Program City CampgroundsCommunity Recreation COVID-19 Hickerson Memorial Cemetery
- Library Parks & Trails Public Safety Fire Police Emergency Information
- Events & Activities City Calendar Library Calendar Recreation Calendar Doing Business in Homer Sister City Program Coast Guard City
-
- Departments
-
Government
-
- Office of the Mayor City Council City Clerk's Office Committees & Task Forces
- Commissions & Boards ADA Advisory Board Economic Development Advisory Commission Library Advisory Board Parks, Art, Recreation & Culture Advisory Commission Planning Commission Port & Harbor Advisory Commission
- Homer City Code Public Meetings Agendas & Minutes Invitations to Bid & RFPs
-
- How Do I?
Memorandum 11-072 Soundview Avenue/Woodard Creek Culvert Replacement Contract Award
Memorandum ID:
11-072
Memorandum Status:
No Status
Related Meetings
Related Ordinances/Resolutions
Details
CITY OF HOMER
PUBLIC WORKS TELEPHONE (907)235-3170
3575 HEATH STREET HOMER, AK 99603 FACSIMILE (907)235-3145
MEMORANDUM 11-072
To: Walt Wrede, City Manager
From: Carey Meyer, Public Works Director
Date: May 16, 2011
Subject: Soundview Avenue/Woodard Creek Culvert Replacement
Construction Contract Award Recommendations
The City opened bids for this project on May 5. Four bids were opened and read:
Peninsula Construction $353,885 Kenai, AK
Prosser-Dagg $309,915 Palmer, AK
Green Construction $215,699.37 Homer, AK
East Road Services $370,680 Homer, AK
Engineer’s Estimate $236,095
Green Construction was found to be the low responsive bidder. Public Works has reviewed the qualifications and abilities of Green Construction and find that the firm is qualified to complete the work. The low bid for this project is within the budget established by the City Council.
Recommendations:
The City Council award the construction contract for the Soundview Avenue/Woodard Creek Culvert Replacement project to Green Construction, of Homer, Alaska in the amount of $215,699.37;
and authorize the City Manager to execute all appropriate documents to complete construction.
Fiscal note: $36,500.37, Acct. No. 256-381; Water/Sewer Reserve Account
$179,199, Acct. No. 160-771; HART