A Resolution of the City Council of Homer, Alaska, Awarding the Contract for the Karen Hornaday Park Red Shed Removal to the Firm of Arctic General Contracting of Ninilchik, Alaska, in the Amount of $3,250 and Authorizing the City Manager to Execute the Appropriate Documents. City Clerk/Public Works Director.
CITY OF HOMER
HOMER, ALASKA
City Clerk/
Public Works Director
RESOLUTION 12-080(S)
A RESOLUTION OF THE CITY COUNCIL OF HOMER, ALASKA, AWARDING THE CONTRACT FOR THE KAREN HORNADAY PARK RED SHED REMOVAL TO THE FIRM OF ARCTIC GENERAL CONTRACTING OF NINILCHIK, ALASKA, IN THE AMOUNT OF $3,250 AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE APPROPRIATE DOCUMENTS.
WHEREAS, In accordance with the Procurement Policy the Invitation to Bid was advertised in the Homer Tribune on August 15 and 22, 2012, posted on the Clerk's home page, and sent to an in-state plans room; and
WHEREAS, Bids were due on September 6, 2012 and eight bids were received; and
WHEREAS, Bids were opened and the firm of Arctic General Contracting was determined to be the low responsive bidder and found to be qualified to complete the work; and
WHEREAS, This award is not final until written notification is received by the firm from the City of Homer.
NOW, THEREFORE, BE IT RESOLVED, that the City Council of Homer, Alaska, approves the award of the Karen Hornaday Park Red Shed Removal Project to the firm of Arctic General Contracting of Ninilchik, Alaska, in the amount of $3,250 and authorizes the City Manager to execute the appropriate documents.
PASSED AND ADOPTED by the Homer City Council this 10th day of September, 2012.
CITY OF HOMER
_____________________________
JAMES C. HORNADAY, MAYOR
ATTEST:
______________________________
JO JOHNSON, CMC, CITY CLERK
Fiscal Note: $3,250, Account No. 151-776.