Resolution 11-050 Contract Award Soundview/Woodard Creek Culvert Replacement

Summary

A Resolution of the City Council of Homer, Alaska, Awarding the Contract for the Soundview Avenue/Woodard Creek Culvert Replacement Project to the Firm of Green Construction of Homer, Alaska in the Amount of $215,699.37 and Authorizing the City Manager to Execute the Appropriate Documents. City Clerk.

Ordinance/Resolution ID: 
11-050(S)
Ordinance/Resolution Status: 
Adopted
Effective Date: 
05/24/2011
File Attachments: 
Postponed Until: 
05/24/2011

Details

CITY OF HOMER
HOMER, ALASKA

City Clerk

RESOLUTION 11-050(S)

A RESOLUTION OF THE CITY COUNCIL OF HOMER, ALASKA, AWARDING THE CONTRACT FOR THE SOUNDVIEW AVENUE/WOODARD CREEK CULVERT REPLACEMENT PROJECT TO THE FIRM OF GREEN CONSTRUCTION OF HOMER, ALASKA, IN THE AMOUNT OF $215,699.37 AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE APPROPRIATE DOCUMENTS.

WHEREAS, The Invitation to Bid was advertised in the Homer Tribune on April 6 and 13, 2011 and posted on the City’s website as required by the City’s Procurement Manual; and

WHEREAS, The project will complete the Soundview Avenue/Woodard Creek culvert replacement; and

WHEREAS, Green Construction  was determined to be the low responsive bidder; and

WHEREAS, This award is not final until written notification is received by Green Construction of Homer, Alaska from the City of Homer.

NOW, THEREFORE, BE IT RESOLVED, that the City Council of Homer, Alaska, approves the award of the contract for the Soundview Avenue/Woodard Creek Culvert Replacement to the Firm of Green Construction of Homer, Alaska in the amount of $215,699.37 and authorizes the City Manager to execute the appropriate documents to complete construction.

PASSED AND ADOPTED by the Homer City Council this 25th day of May, 2011.

CITY OF HOMER

_____________________________
JAMES C. HORNADAY, MAYOR
ATTEST:

______________________________
JO JOHNSON, CMC, CITY CLERK

Fiscal Note: $215,699.37, Acct. No. 160-766