City of Homer

 

    Memorandum No. 03-94

To:          Mayor Cushing & City Council

From:      Walt Wrede, City Manager

Date:       May 28, 2003

                     Re:            CIP List Development

It’s time to begin work on the Capital Improvement Plan for 2004-2009. As you know, this annual process involves the public, the Council, the Commissions, and local non-profit organizations and agencies helping to identify capital projects of particular benefit to the Homer community. Anne Marie Holen will once again be coordinating the planning process in this office. Our goal is to have a list of projects approved in time to meet the October 1 application deadline for a state Capital Project Matching Grant.

Please find attached a proposed schedule for developing the 2004-2009 CIP and the 2005 Legislative Request. Council approval of this schedule is the first step in the Capital Improvement Planning process.


RECOMMENDATION: Approve 2004-2009 CIP/2005 Legislative Request Development Schedule.

CITY OF HOMER
2004-2009 CAPITAL IMPROVEMENT PLANNING PROCESS
2005 LEGISLATIVE REQUEST DEVELOPMENT SCHEDULE

 

                        ACTION                                                                                TIMEFRAME

City Council approval of schedule                                                                            June 9

Distribution of memo and packets to departments and agencies                                June 10

Project descriptions due to Administrative Assistant                                                 July 1

Commission review of proposed projects:

      Planning Commission                                                                                         July 16

      Parks and Recreation Commission                                                                     July 17

      Port and Harbor Commission                                                                             July 23

      Library Advisory Board                                                                                     August 5

Administrative review and compilation                                                                     August 11-15

City Council worksession to review proposed projects                                            August 25

Public Hearing on CIP/Legislative request/Matching Grant request                           September 8

Adoption of resolutions by City Council                                                                   September 22

Capital Project Matching Grant application due                                                        October 1

Administrative compilation of CIP and Legislative Request                                       October 1-31

Distribution of CIP                                                                                                  November 1

Distribution of Legislative Request                                                                           January 2004