Memorandum No.
03-94
To: Mayor Cushing & City Council
From: Walt Wrede, City Manager
Date: May 28, 2003
![]()
Re: CIP List Development
It’s
time to begin work on the Capital Improvement Plan for 2004-2009. As you know,
this annual process involves the public, the Council, the Commissions, and
local non-profit organizations and agencies helping to identify capital
projects of particular benefit to the Homer community. Anne Marie Holen will
once again be coordinating the planning process in this office. Our goal is to
have a list of projects approved in time to meet the October 1 application
deadline for a state Capital Project Matching Grant.
Please
find attached a proposed schedule for developing the 2004-2009 CIP and the 2005
Legislative Request. Council approval of this schedule is the first step in the
Capital Improvement Planning process.
RECOMMENDATION: Approve 2004-2009 CIP/2005 Legislative Request Development
Schedule.
CITY
OF HOMER
2004-2009 CAPITAL IMPROVEMENT PLANNING PROCESS
2005 LEGISLATIVE REQUEST DEVELOPMENT SCHEDULE
ACTION TIMEFRAME
City
Council approval of schedule June
9
Distribution
of memo and packets to departments and agencies June
10
Project
descriptions due to Administrative Assistant July
1
Commission
review of proposed projects:
Planning Commission July
16
Parks and Recreation Commission July
17
Port and Harbor Commission July
23
Library Advisory Board August
5
Administrative
review and compilation August
11-15
City
Council worksession to review proposed projects August
25
Public
Hearing on CIP/Legislative request/Matching Grant request September 8
Adoption of
resolutions by City Council September
22
Capital
Project Matching Grant application due October
1
Administrative
compilation of CIP and Legislative Request October
1-31
Distribution
of CIP November
1
Distribution
of Legislative Request January
2004