To:
Walt
Wrede, City Manager
From:
Carey Meyer, Public Works Director
Date:
May 10, 2004
Subject: Proposed
Animal Shelter
Construction Funding and
Authorization
![]()
Earlier this year,
the City Council established a budget and authorized Public Works to
proceed
with design of the new animal shelter.
The design is complete, and as promised we are back to present
the final
design. Attached is the final floor
plan and building elevations. Below is
the approved budget:
Shelter
Building (3272 SF x $175/sf)
$
572,600
Dog
Runs (900 SF x $95/SF)
$ 85,500
Earthwork
(2,500 CY x $9/CY)
$ 22,500
Slope
Erosion Control
$ 20,000
Site Improvements (parking, water/sewer, drainage)
$
75,000
Electrical/Telephone service
$ 30,000
Demolition of Existing Facility
$
0
Subtotal -
Construction Budget
$
805,600
Animal Shelter Building
$ 64,000
Civil Site Improvements
$ 12,000
Design Survey/Geotechnical Study
$ 15,000
Construction Inspection
$ 8,000
Subtotal - Design Budget
$ 99,000
Subtotal
$
904,600
Contingency (5%)
$ 45,000
TOTAL PROJECT BUDGET
$
949,600
The recent increase
in the cost of steel, lumber and copper has put pressure on our budget. By eliminating some of the furnishings (some
of the painting, lockers, sinks, cabinets, etc.) and some exterior work
(seeding, landscaping, gutters/downspouts); the project is within the
approved
budget. The eliminated items can and
will be accomplished by animal shelter volunteers.
Recommendation: The Council identify a funding mechanism to
augment available funds and authorize the City Manager to execute all
documents
necessary to bid and construct the facility.