                        Construction Funding and Authorization


 


Earlier this year, the City Council established a budget and authorized Public Works to proceed with design of the new animal shelter.  The design is complete, and as promised we are back to present the final design.  Attached is the final floor plan and building elevations.  Below is the approved budget:

Construction Budget:

Shelter Building (3272 SF x $175/sf)                  $ 572,600

Dog Runs (900 SF x $95/SF)                                               $   85,500

Earthwork (2,500 CY x $9/CY)                                             $   22,500

Slope Erosion Control                                                         $   20,000

                Site Improvements (parking, water/sewer, drainage)     $   75,000

                Electrical/Telephone service                                              $   30,000

                Demolition of Existing Facility                                           $            0

                Subtotal - Construction Budget                                        $ 805,600

Design Budget:

                Animal Shelter Building                                                      $   64,000               

                Civil Site Improvements                                                      $   12,000                    

                Design Survey/Geotechnical Study                                  $   15,000               

                Construction Inspection                                                     $     8,000               

Subtotal - Design Budget                                                   $   99,000

               

Subtotal                                                                                 $ 904,600

Contingency (5%)                                                              $   45,000

 

TOTAL PROJECT BUDGET                                            $ 949,600

 

The recent increase in the cost of steel, lumber and copper has put pressure on our budget.  By eliminating some of the furnishings (some of the painting, lockers, sinks, cabinets, etc.) and some exterior work (seeding, landscaping, gutters/downspouts); the project is within the approved budget.  The eliminated items can and will be accomplished by animal shelter volunteers.

 

Recommendation:  The Council identify a funding mechanism to augment available funds and authorize the City Manager to execute all documents necessary to bid and construct the facility.