MEMORANDUM 05-52

 

To:                   Walt Wrede, City Manager

From:               Carey Meyer, Public Works Director

Date:                January 28, 2005

Subject:            Spit Restrooms – Request for Additional Funding


 


As you are aware, we have been working since late last summer and through the winter constructing the new restroom facilities on the Spit at Ramp 6, Ramp 4 and at the top of the Load/Launch Ramp.  The facilities are partially funded with grant monies from State of Alaska Department of Fish & Game with some additional funds from the Harbor Reserve Account.  The total AK F&G grant funding for this project is $293,000.(for all three restroom facilities) and the Council approved $133,000 (for the Ramp 6 restroom).  Total funding available is $426,000.  As of February 18, 2005 we have expended a total of $429,134 (see detailed breakdown below). 

Launch Ramp               Ramp 6            Ramp 4

 

ROMTEC                                $   50,010                    $    81,093       $    99,892*     * - includes design

Building Kits & fixtures                                                                                          and other misc.

                                                                                                                                         expenses.

Site Work, Elec.,

Concrete, Materials                  $   23,599                    $    26,840       $    21,326

 

Force Account Labor               $   30,586                    $    58,523       $    37,265      

                                                                                                                                        

            Totals (2/18/05)           $ 104,195                    $  166,456       $  158,483      

 

The cost to complete the restrooms is $59,000.  This work includes heating, hot water, plumbing, and misc. sidewalk/finishing work.  AK F&G has indicated that an additional $30-40,000 will be available to cover additional work completed.

 

Except for the interior heating and plumbing work (which the State building inspector requires be accomplished by journeyman plumbers), all additional labor will be accomplished by Public Works crew.  The plumbing and heating work will be accomplished by a local contractors.  All three restrooms will be heated (year-round operation); have piped water and sewer (no long term holding tank pumping costs); have hot water; will be handicapped accessible; and are designed to be low maintenance.

 

Recommendation:  The City Council authorize an additional expenditure of $59,000 from the Harbor Reserve Account to complete this project and authorize requesting/accepting $40,000 in additional

grant funds from AK F&G to help cover cost to complete.