TO: Mayor Hornaday – Homer City Council
FROM: Walt Wrede
DATE: May 3, 2005
SUBJECT: Bid Award / Library
The Agenda for the May 9th meeting contains a resolution awarding the library construction contract to Jay-Brant Company. As you know from our discussion at the last meeting, there is a difference of $890,023 between the amount of money the City has in hand and the cost of the project. This is essentially the difference between the engineer’s estimate and the low bid.
The City staff has spent the last two weeks conducting research, consulting with attorneys, talking to federal funding agencies, and generally reviewing all of the City’s options regarding how we might bridge this gap. It is important to remember that we cannot negotiate with the contractor regarding possible cost savings and efficiencies until we actually award a contract. We believe that substantial savings can be found and that the contractor is very willing to work with us to find ways to reduce costs.
The purpose of this memo is to provide a recommendation and strategy to the Council on how the gap might be bridged through a combination of budget cutting and new revenues. First, lets review the current situation. The available funds shown below reflect what remains in the project budget for construction. Architectural costs have been backed out because those funds are largely expended.
Sale of Library $500,000
Foundation Grants 1,325,000
Government Grants 2,246,043 (less architecture expenses)
USDA 30 Year Loan 1,700,000
Fundraising 640,920
Total
Funds Available
$6,411,963
Construction (low bid) $6,146,889
Architecture Services -- ($569,161 / expended)
Construction Management 315,000
1% Art 43,777
Site Work / Materials 115,000
Interim Financing / Interest --
Admin. And Legal Expenses --
Equipment/Furnishing 250,000
Contingency 431,320
Project
Balance
$7,301,986
Net
($7,301 - $6,146,889) <
$890,023>
II. RECOMMENDATION:
The administration proposes to close the gap by taking the following steps:
* Increase USDA Loan Amount to full authorization <500,000>
* Increase sale of Library to appraised value < 75,000>
* Take Deductive Alternative < 37,500>
* Reduce Equipment/Furnishing Budget <200,000>
* Reduce Contingency Budget <77,523>
Net
(Budget Gap) $ 0
NOTE: The Contingency and Equipment/Furnishing line items can be reduced now because they were not part of the construction bid package. They were simply part of the City’s overall project budget.
As I noted above, the staff spent a great deal of time evaluating all of the available options. Following are some important considerations and assumptions that we rely on in making this recommendation.
The steps the Council needs to take to implement this plan and award a bid to Jay-Brant are all included on the May 9th Agenda. There are five library related action items on the Agenda and they are arranged so that you can deal with all of the money issues first before you take the vote on awarding the bid. The five steps are: