Contract Award Recommendations

           


 


Public Works opened bids for the above referenced project on September 21.  Below are the results:

           

            Moore & Moore Services                    Homer, AK                              $   38,222.70  

            Arno Construction, Inc.                        Homer, AK                              $   41,560.00  

            East Road Services, Inc.                       Homer, AK                              $   51,000.00

            Twin Peaks Construction, Inc.  Homer, AK                              $   57,171.00

            Alaska Pioneer Contractors, Inc.          Kasilof, AK                              $   62,157.00

            Coldfoot Environmental Services           Anchorage, AK                        $   70,277.50

            Endries Company                                 Soldotna, AK                           $   83,850.00

            Herndon Construction LLC                  Homer, AK                              $   86,945.00

            Alaska Demolition                                Anchorage, AK                        $   96,000.00

            Suulutaaq, LLC                                    Anchorage, AK                        $ 502,379.00  

 

Public Works has reviewed the bids and evaluated the responsiveness of each bidder. The apparent low responsive bidder is Moore & Moore Services.  The engineer’s estimate was $85,000.

 

This project will be funded from the account # 156-396.  The budget for this work was established in the 2006 budget at $40,000.  The City has expended approximately $8000 to date on an environmental survey of the buildings and bid preparation and advertising costs.  Based on the low bid received and providing for a small contingency, the project is now anticipated to be $47,500.

 

Recommendation:  The City Council should authorize the City Manager to issue a Letter of Intent to Award to Moore & Moore Services, Homer, Alaska.  Upon meeting the conditions of the Bid Documents, the City Manager should be authorized to award the contract to Moore & Moore Services in the amount of $38,222.70; issue a Notice to Proceed, and execute all required documents needed to complete this project (in accordance with this and previous authorizations by the City Council). 

 

Award Date…………………………………….………………..……..September 25, 2006

Pre-Construction and Notice to Proceed………………………………..     October 1, 2006

Completion……………….………………………………….….  …..   November 22, 2006