                        Cost Estimates 2006


 


As discussed at the last Meeting of the Whole, Public Works will not be able to add any significant width to the roads scheduled for repaving this summer.  There is not sufficient road prism width to accomplish the construction of 6 foot wide pedestrian walkways. Adding additional road width would infringe into the surface drainage ditches and require considerable engineering and road reconstruction costs.  Below is a breakdown of the costs of completing pavement replacement and the cost of reconstruction to provide for pedestrian improvements:

 

Original Project

                                                                                       LF     Repaving Cost*   Reconstruction Cost**

 

Main Street                  Pioneer to Mountain View        2750         $125,000                $   990,000

Bayview Avenue           Main to Kachemak Way           1930         $  92,000                $   695,000

Kachemak Way           Bayview to Pioneer                   2700         $129,000                $   972,000

Ben Walters Lane         East End to Mark White           3100         $140,000                $1,116,000

Rochelle Road              East End to High School           1405         $  74,000                $   506,000

Upper Heath Street      Pioneer to High School   600         $  40,000                $   225,000

 

Requested Additions

 

Soundview Avenue       Mulliken to Forest Glen              650         $  36,000                $   234,000

Waddell Street             Sterling Hwy to Post Office         600         $  24,000                $   216,000         

 

                                                            Total Project Cost             $660,000                $4,954,000

 

*    Repaving could provide two 10’ lanes and a 4’ shoulder.

 

**  Reconstruction would require excavation and backfill, installation of storm drain system, storm water treatment facilities, curb/gutter, and concrete sidewalks (similar to ADOT Bartlett/Hohe Project).

 

Recommendation:  Public Works recommends that we repave the six roads in the original project and the two additional roads shown above to maintain the road improvements we currently have using HARP funds.   The creation of pedestrian walkways along streets in Homer will require considerable funding and a long term commitment of resources.