                        Request for ADWF Loan Application Authorization

 


The City (starting in 2005) secured funding for this project.  In the State’s FY 06 budget, $480,000 was obtained (70% State/30% City) for design. In the State’s FY 07 budget, $2,072,000 was obtained (50% State/50% City) for final design and construction. In the State’s FY 08 budget, $2,500,000 was obtained (50% State/50% City) for construction.  The City has requested an additional $2,400,000 (50% State/50% City) for construction in the State’s FY 09 budget.

 

Total funding in place (with the FY 09 requested funding) - $7,452,000 ($3,822,000 State/$3,630,000 City).  The City can secure low interest loans (2.5%) through the Alaska Drinking Water Fund (ADWF) for the City’s share of the funding already secured and the remainder of the cost of the project.  The expected construction cost of the project is $9,172,848.

 

The total budget for this project is as follows:

 

            City Admin./Support Contracts             $      250,865

Design                                                              $      842,645

Construction                                                     $   9,172,848*

Inspection                                                         $      650,000

Contingency (5%)                                             $      458,642

 

            Total Project Budget                             $ 11,375,000

 

The schedule for the project is anticipated as follows:

 

            Complete Final Design of WTP facility                                      December, 2007

            Open Bids for Construction of WTP facility                                           February, 2008

            Award Bids for Construction of WTP facility                             February, 2008

            All Grant and Loan Funds in Place                                                        February, 2008

            Issue Notice to Proceed for WTP facility                                              March, 2008

            Start Construction of WTP facility                                                         May, 2008

            Procured Treatment Equipment Arrives in Homer                                  June, 2008

            Construction of WTP facility Complete                                     November, 2008

 

 

 

 

Funding for the project is anticipated as follows:

 

                                                            City Portion                  State Portion                Total

 

ADEC FY 06 Grant                 $    144,000                 $    336,000                 $      480,000

ADEC FY 07 Grant                 $ 1,036,000                 $ 1,036,000                 $   2,072,000

ADEC FY 08 Grant                 $ 1,300,000                 $ 1,300,000                 $   2,600,000

ADEC FY 09 Grant                 $ 1,200,000                 $ 1,200,000                 $   2,400,000

ACWF Loan (remaining)          $ 3,823,000                 $               0                 $   3,823,000

 

                                                            $ 7,503,000*               $ 3,872,000                 $ 11,375,000

 

* - This is the anticipated ADWF loan amount

 

Recommendations: 

 

The City Council approve a resolution authorizing the ADWF loan application and the acceptance of the future loan offer from the Alaska Department of Environmental Conservation.

 

With the approval of the resolution, the City will apply for the ADWF loan in December, 2007and accept the loan offer in February, 2008.