The Ocean Drive Loop
Sewer LID and the Peterson Sewer LID have been constructed. All costs for these two projects are
known. This memo documents the costs for
each project and determines the per lot assessments.
Attached is a map
showing the lots that where contained within original boundaries of each LID
and the lot configurations as they exist today.
The Ocean Drive Loop LID was approved in 2004 and the Peterson LID was
formed in 2007.
The costs of each
project are outlined below:
The actual cost of the two projects are very close to the cost
estimated when the LID’s were formed.
The costs per lot for each of the projects is shown below:
The actual
assessments are higher than projected not because the costs where higher, but
because there are fewer lots now. Much
re-platting occurred during the completion of this project (see attached
maps).