|
CITY
OF HOMER
PUBLIC WORKS TELEPHONE
(907)235-3170
3575 HEATH STREET HOMER, AK 99603 FACSIMILE
(907)235-3145
To:
From:
Date:
Subject: Homer
Water Treatment Plant Improvements Project
Budget Approval –
Funding Expectations – Project Status
Background:
Water treatment plant capacity struggles to meet summer peak water demand. More stringent federal drinking water
regulations are now in effect and the plant struggles to comply with these new
standards (especially in the summer).
The Homer Water/Sewer Master plan documents the difficulties the system
has had meeting the new regulations, presents evidence that summer reservoir
raw water quality continues to deteriorate, and suggests that more capacity and
better treatment capabilities are needed.
The City (starting
in 2005) secured funding for this project.
In FY 06, $480,000 was obtained (70% State/30% City) for design. In FY
07, $2,072,000 was obtained (50% State/50% City) for final design and
construction. Currently the Governor’s budget includes an additional $2,500,000
(50% State/50
In 2006, the
Consultant (
Discussion: The project consists of the construction of a
new water treatment plant that will utilize membrane filtration
technology. The construction of the
project will consist of two parts; competitive procurement of the membrane
treatment equipment (through a RFP process); and construction of the building
facility and installation of the membrane treatment equipment through the
normal competitive bidding process.
Attached are
drawings showing the proposed site plan for the facility, a floor plan of the
treatment plant building, and exterior view of the facility.
Public Works, in
conjunction with this project, is attempting to acquire large pieces of
property within the Bridge Creek Water Shed.
This ownership of this property will protect the watershed from
development and provide for a small parcel on which the new treatment plant
facility will be constructed. Funding for this acquisition will be through a
loan from the ACWF.
The schedule for the
project is anticipated as follows:
Issue Equipment Procurement
Documents to suppliers
Initiate Final Design of WTP
facility
Make application for ADWF loan
Receive Equipment Procurement
Proposals
Award Equipment Procurement Contract
Complete Final Design of WTP
facility
Open Bids for Construction of WTP
facility
Award Bids for Construction of WTP
facility
All Grant and Loan Funds in Place
Issue Notice to Proceed for WTP
facility
Start Construction of WTP facility
Procured Treatment Equipment Arrives
in Homer
Construction of WTP facility
Complete
Funding for the
project is anticipated as follows:
City
Portion State Portion Total
ADEC FY 06 Grant $ 144,000 $
288,000 $ 480,000
ADEC FY 07 Grant $ 1,036,000 $ 1,036,000 $ 2,072,000
ADEC FY 08 Grant $ 1,300,000 $ 1,300,000 $ 2,600,000
ACWF Loan $
2,338,000 $ 0 $ 2,338,000
$4,818,000 $ 2,624,000 $ 7,490,000
(Note:
The City has requested additional federal grant funding assistance through our
federal representatives that could reduce the amount of loan funding required
for this project.)
Recommendations:
1)
The City
Council establish the overall budget for the water
treatment plant improvement project at $7,490,000.
2)
The City
Council approve the award of the final design of the project to
3)
City
Council be prepared to award the procurement of
membrane water treatment plant equipment
4)
City
Council be prepared to authorize the acceptance of a
loan offer from the ADWF early in May in the amount of $5,000,000.
5)
City
Council be prepared to award contract for construction
of the water treatment plant facility
6)
City
Council be prepared to award a construction
inspection/administration contract to