Subject: Paintbrush Booster Station
Improvements
Construction Contract Award Recommendations
Public Works opened bids for the above referenced project on April 19. Below are the results:
Twin Peaks
Construction, Inc.
Sunland Development Co. LLC Homer, AK $ 127,700
Public Works has reviewed the bids and evaluated the responsiveness of each bidder. The apparent low responsive bidder is Twin Peaks Construction, Inc. The Engineer’s estimate is $85,000.
Budget Actual
Purchase Booster Station $66,000 16,900
Installation $44,500 77,965
Design and Construction Inspection $25,000 21,536
Contingency 0 15,000
Total Project Cost = $135,500 $131,401
The City Council authorized the expenditure of $135,500 from the HAWSP fund to complete this project. The cost will be paid for directly by the HAWSP fund (163-175).
Recommendation: The City Council should authorize the City Manager to issue a Letter of Intent to Award to Twin Peaks Construction, Inc. Upon meeting the conditions of the Bid Documents, the City Manager should be authorized to award the contract to Twin Peaks Construction, Inc. in the amount of $77,965; issue a Notice to Proceed, and execute all required documents needed to complete this project (in accordance with previous authorizations by the City Council).