City of Homer
Memorandum 08-131
In keeping with
decisions made by the City Council at the September 15 Special Meeting, I have prepared
a new draft CIP with the following changes from the previous version:
· Projects scheduled for completion after
2014 have been removed from the main CIP. These projects are now listed in an
appendix titled “City of Homer Long Range Capital Projects.” Seventeen
projects are listed. NOTE: Some CIP
projects in the previous draft contained elements to be completed during the
2009-2014 period as well as elements scheduled for completion after
2014. All of the “after 2014” items are now listed in the Appendix; however, I
have not yet re-written the main CIP project descriptions. I don’t think this
will be hard to do. In the meantime, I have marked those pages with handwritten
notes.
· I have updated the project table (in the
Appendix) to add a new column that says “Later Years.” Also, the table no
longer includes non-City projects (e.g., state roads or non-profit
projects). Priority Level boxes and Years are not yet filled in. I would like
feedback from Council on whether “Later Years” projects should be mixed in with
others in the table (as they are currently) or listed at the end of the table
or not at all.
The following
bullet points are repeated from my last memo (of Sept. 9):
· Projects are grouped into
seven sections: Local Roads, Trails, Structures,
Utilities, Equipment, State Transportation Projects, and Other Projects. (In
this CIP, all of the “Other Projects” are ones proposed by non-profit
organizations. However, in the future this section could also contain projects
related to the college, Kachemak Bay Research Reserve, and other organizations
that are not non-profits but still fall into the “non-City” category.)
· New projects (both City and non-City
projects) are attached separately. Council approval is required for these
projects to be included in the CIP:
PROJECT: |
SUBMITTED BY: |
Beluga Slough Trail Reconstruction |
Planning Technician Julie Engebretsen and |
Bishop’s Beach Park Picnic Shelter |
Julie Engebretsen, Parks & Rec Commission, and Tammy
Hagerty |
Brush/Wildland Firefighting Truck |
Fire Chief Bob Painter |
Community Recreation/Multi-Use Center |
Community Schools Coordinator |
Fire Engine 4 Refurbishment |
Fire Chief Bob Painter |
Fire Pump Testing Trailer |
Fire Chief Bob Painter |
Fishing Lagoon Improvements |
Fish and Game biologist Nicky Szarzi |
Ramp 3 Gangway and Approach Replacement |
Port & Harbor Director |
Sewer Treatment Plan – Bio-solids Treatment Improvements |
Public Works Director Carey Meyer |
Water Storage/Distribution Improvements |
Public Works Director Carey Meyer |
Lake Street Reconstruction (State road project) |
Public Works Director Carey Meyer |
Kevin Bell Arena Floor Upgrade |
Cinda Eckert, Homer Hockey Association |
Pratt Museum Renovation |
Heather Beggs, Pratt Museum |
Senior Independent Housing |
Fred Lau, Homer Senior Citizens |
South Peninsula Hospital |
Derotha Ferraro, South Peninsula Hospital |
· Several projects that were in the 2008-2013 CIP have been
deleted from this draft:
PROJECT: |
REASON: |
Reber
Trail |
Funded
through state grant and HART program |
Engine
4 Replacement |
Funded
through state municipal energy grant |
Water
Treatment Plant |
Funded
through combination of state legislative appropriations and DEC loans |
South
Peninsula Hospital Helistop |
Funded
by |
Williamsport–Pile
Bay Road Rehabilitation |
Funded
through federal transportation earmarks |
· New
“priority” terms. Many people have noted that the “need terms” used in the
past are confusing. Therefore, the new draft CIP has adopted different terms
that are intended to be simpler and more intuitive. Each project is labeled as
either Level 1 Priority (highest), Level 2 Priority, or Level 3 Priority.
Factors
to take into account when setting priority level include:
·
Will the project correct a problem that poses a clear danger to human
health and safety?
·
Will the project significantly enhance City revenues or prevent
significant financial loss?
·
Is the project widely supported within the community?
·
Has the project already been partially funded?
·
Is it likely that the project will be funded only if it is identified as
being of highest priority?
·
Has the project been in the CIP for a long time?
·
Is the project specifically recommended in other City of Homer
long-range plans?
·
Is the project strongly supported by one or more City advisory bodies?
In
the end, the Council, in consultation with the City Manager, must weigh all the
factors to determine the priority level for each project. For this draft, I
have worked with the City Manager to assign labels that the Council may want to
review before the CIP is finalized.
· Project “schedule”
dates. Based on his knowledge of existing
conditions and other factors, the City Manager has proposed schedule dates for
all City projects that reflect more realistic timeframes than past CIPs have
shown. Many of the projects are now shown as taking place after 2014 (i.e.,
beyond the 6-year planning period covered by this CIP.)
As
reflected in the new dates, it is recommended that major City buildings
be completed in this order:
In the next 6 years:
Port and Harbor building
City Hall
Skyline Fire Station
Beyond 2014 (but within 10 years):
Public Works Complex
Police/Fire Hall Complex
Likewise,
it is recommended that public restrooms be completed in this order:
In the next 6 years:
Fish Dock (demonstrated
need, partial funding secured)
Downtown (demonstrated need
for tourist and pedestrian-oriented downtown)
Mariner Park (beach,
campground, and Spit Trail users, heated for shoulder seasons
Jack Gist Park (new park,
heavy projected use starting next year)
Beyond 2014:
Hornaday Park (still
serviceable, replacement should be heated for shoulder seasons)
Ramp 2 (still serviceable)
Ramp 5 (still serviceable)
Spit Trailhead at Kachemak
Drive
End of the Road Park
·
Recommendations from City Commissions. (Note:
In most cases, Commissions did not consider proposed new projects, since those
projects had not yet been drafted.)
The Planning Commission recommended the following CIP projects
in priority order:
1. Water Treatment Plant
Upgrade/Alternate Water Source
2. Deep Water Dock Expansion, Phase 1
3. Main Street Reconstruction
4. Homer Intersection Improvements
The following projects, in no particular order, are also important to the
Commission: Town Center
Infrastructure, East Boat Harbor, Firefighting Enhancement–Aerial Truck; Paving
Freight Dock Road; Public Restrooms; Skyline Fire Station; Spit Trail
Completion; Sterling Highway Reconstruction–Anchor Point to Baycrest Hill.
The Parks and Recreation Commission ranked their top eight
projects as follows:
1. Karen Hornaday Park Drainage
Improvements
2. Kachemak Drive Separated Pathway;
3. Jack Gist Park;
4. Mariner Park;
5. East Trunk Trail;
6. Homer Greenhouse;
7. Main Street Reconstruction
8. Homer Intersection Improvements
The Library
Advisory Board ranked their top five projects as follows:
1. Aerial Fire Truck
2. Homer Intersection Improvements
3. Public Restrooms–Downtown
4. Homer Greenhouse
5. Haven House
The
Port and Harbor Commission ranked their top seven projects as follows:
1. Deep Water Dock Expansion, Phase 1
2. Harbor Float Replacement, Phase 1
with Ramp 3 Gangway and
Ramp 3 Approach Replacement added
3. Harbor Entrance Erosion Control
4. Pioneer Dock Fenders
5. Spit Trail Completion/Harbor Pathways
6. East Boat Harbor
7. Williamsport–Pile Bay Road
The
Economic Development Commission ranked their CIP priorities as follows:
1. Alternative Water Source
2. Firefighting Enhancement–Aerial
Truck
3. Paving Freight Dock Road
4. (tie): Main Street Reconstruction,
Intersections Improvement, Kachemak Drive
Rehabilitation/Pathway,
Williamsport–Pile Bay Road, Rescue Systems Upgrade, and
Bridge Creek Watershed Land
Acquisition
5. Skyline Fire Station
·
Reminder about State funding for
water/sewer projects: The City receives 50 points in the DEC scoring system
if the project has been identified as our number-one capital improvement priority;
without the 50 points it is unlikely a project will score high enough to
receive funding.
·
Remaining Steps in 2009-2014 Capital
Improvement Planning Process: The public hearing for the CIP is scheduled
for the September 22 City Council meeting. Adoption of the CIP and the FY 2010
legislative priority list is scheduled for October 13.