|
CITY
OF
PUBLIC WORKS TELEPHONE
(907)235-3170
To:
From:
Date:
Subject: Homer
Water Treatment Plant Improvement Project
Construction Contract
Award Recommendations
The City opened bids
for this project on March 6. Two bids
were received:
Bid
Amount
Udelhoven Oilfield
System Services, Inc. $8,639,359
Alaska Mechanical,
Inc. $9,793,000
Engineer’s Estimate $7,672,000
The lowest
responsive bid is 12.6% above the engineer’s estimate.
The City’s options
are 1) reject all bids and rebid current project, 2) redesign project to significantly
reduce price and rebid, 3) identify ways to reduce price, find reasonable
alternative funding sources, and award with alternative funding at a lower
cost.
Rebidding the current
project would allow additional contractors to bid the project. There were three other interested prime
contractors that could not put a bid together because they could not get a bid
from any mechanical subcontractors.
Rebidding does not guaranty that more bidders will participate or that
the existing bidders will continue to participate. There is no guaranty that rebidding will
result in lower bids, rebidding could result in higher bids.
Scaling down the project to bring the price closer to the engineer’s estimate would require significant revisions. Important components of the project would most probably need to be sacrificed. A scaled-down project would not provide the City with a practical and long-lasting water treatment plant.solution. Postponing the project could impact the City’s ability to continue to meet the new more stringent drinking water quality regulations.
The project budget
did include a contingency. Some of this
contingency could be used to cover the additional cost. Some efficiencies can be implemented to
reduce budgeted inspection costs to help meet the higher cost of construction.
Some portions of the construction project normally would be completed using
funds from the depreciation and reserve accounts. Paying for the removal of sludge from the
existing lagoons out of the reserve account would be a reasonable method of funding
the
additional cost and
eliminating the need to borrow money to complete work normally paid for by
depreciation finds. Modifications to the
bid documents reducing risk and removing non-essential components has reduced
the cost of the project to an 8.7% increase over the engineer’s estimate. Discussions continue to formally establish
cost savings.
Recommendations:
The City Council
approve the award of the bid in the amount of $8,339,359 ($300,000 less than
low bid) to the firm of Udelhoven Oilfield System Services, Inc. Authorize City Manager to issue notice of
intent to award.
The City Council
revise the project budget as follows:
Current
Budget Revised Budget
City Admin./Support
Contracts $ 250,865 $ 250,864
Design $ 842,645 $
842,645
Construction $ 7,672,848 $
8,339,359
Treatment Equipment $ 1,500,000 $ 1,500,000
Inspection $ 650,000 $ 550,000
Contingency (5%) $ 458,642 $ 308,642
Funds from Reserve Account $ 0 $ 275,000
Total Project Budget $ 11,375,000 $ 12,066,510
Funding for the
project is anticipated as follows:
City
Portion State Portion Total
ADEC FY 06 Grant $ 144,000 $
336,000 $ 480,000
ADEC FY 07 Grant $ 1,036,000 $ 1,036,000 $ 2,072,000
ADEC FY 08 Grant $ 1,300,000 $ 1,300,000 $ 2,600,000
ADEC FY 09 Grant $
1,200,000 $ 1,200,000 $ 2,400,000
ACWF Loan $
4,320,000 $ 0 $ 4,320,000
Reserve Account Funds $ 275,000 $ 0 $
275,000
$
8,275,000* $ 3,872,000 $ 12,147,000
* -
$8,000,000 ADEC loan at 1.5% over 20 years (currently authorized by the
Council) plus $275,000 from reserve account.