PUBLIC WORKS TELEPHONE
(907)235-3170
To:
From:
Date: December 17, 2007
Subject: New
City Hall/Plaza
Project Status – Budget
– 65% Design Award
The design team is ready
to move forward with the 65% final design.
The intent will be to contract for this design only if the
To this end, Public
Works has established a scope of work and a schedule for this 65% schematic
design. As in previous phases, the City
will contract directly with each firm, with Jay-Brant leading the project
team. The project team has determined
the cost of completing this 65% design work:
Team Member Tasks Assigned 10% Fee 35% Fee 65% Fee
ECI/Hyer (design/public involvement) $ 101,980 $ 202,985 $ 300,000
Jay-Brant (constructability/cost
estimating) $ 28,563 $
63,973 $ 75,000
Seabright Survey (survey/permitting/platting prep) $ 65,288 $ 9,500 $ 0
Total $ 195,831 $ 276,458 $ 375,000
The budget for all
City Hall/Plaza pre-construction services is estimated to be $980,000. We appear to be in line with this
expectation. The public, the City Hall/Town Square Review Committee and City staff
will continue to provide input to the final design.
Once the 65% final
design is approved by the Council, the team expects to be ready to inter into a
Maximum Allowable Cost Contract (MACC)
Recommendation: The City Council should award and
approve this set of contracts with the two firms of ECI/Hyer and Jay-Brant for
the 65% final design and authorize the City Manager to execute all appropriate
documents.