MEMORANDUM 09-10
TO:
Mayor Hornaday / Homer City Council
FROM:
Walt Wrede and Carey Meyer
DATE: January 19, 2009
SUBJECT:
Economic Stimulus Package / Project List
At the last meeting, the Council adopted Resolution 09-10
which approved a list of projects that will be submitted for possible inclusion
in the proposed Federal Economic Stimulus Package. During discussion, the
Council recognized that the list of projects was compiled in a hurry and under
a deadline and expressed a desire to have some additional discussion and
possibly amend and/or supplement the list. In addition to that, new details
have emerged about the package since Resolution 09-10 was adopted that may
influence how the Council may want to amend the list. Those new details
include:
- It now
looks as though projects will need to be “shovel ready” within 180 days (6
months) instead of 90 to 120 days.
- It
appears that water and sewer projects will be emphasized but that money
for them will be appropriated through the existing revolving loan fund,
which Homer has already used extensively. There is some talk about loan
forgiveness under some circumstances.
- It is
now very clear that education and “green” energy and infrastructure
projects will be a high priority.
Following are some comments on various projects that could
be added to the list. Some of them are City projects and others are not. A few
we strongly recommend adding. Others require more discussion with Council.
Recommended City Projects
- Deep
Water Dock: Since it now looks like we might have up to six months to
complete design and permitting, we are more confident that we can get this
done. We recommend that this project be added. We would caution
Council that the money will probably have to be returned if construction
is not complete within two years. Also, the draft resolution promises a
10% local match. This is a $ 20 Million Project (Federal Request $18,
Million) so 10% is $2 Million. Recall that the Council assured Senator
Stevens that it would issue $ 2 Million in Revenue Bonds as a local match.
- Turbine
Electric Project: Recall that
the City received a grant to design this project. Design is currently
underway. Since alternative energy is a high priority in the stimulus
package and we now have additional time to complete design, this project
seems ideal. We recommend that this project be added. The Federal
Request is $400,000 for construction and installation, and connection to
the electric grid.
City Projects Under Consideration
- Other
Water and Sewer Projects: Public Works is considering a number of
projects that would help with maintenance and upkeep of the current
system. These projects would save the City and the ratepayers money in the
future. Examples include repairs to the PRV
Stations and replacement of the water line from the Spit (Council has
already approved design). We will have more detail for you by meeting
time. Since these types of projects are only likely to be funded through
the revolving loan fund, we would not recommend doing them unless the
loans have a provision for loan forgiveness that the City is eligible for.
The HAWSP Fund has enough debt already and depleting the water and sewer
depreciation fund and/or raising rates is not desirable at this time. We
have also discussed adding the new sewer treatment plant project that was
inserted into the CIP List this year. However, Carey does not think it is
possible to have that project ready for bid within 6 months.
Other Projects
- The
Kachemak Ferry: At the time this was written, I had not yet spoken to
Michael Beal, the consultant who is working on the Kachemak Ferry Project.
I hope to have more information about this, including where they are on
the design process, by meeting time. One thing to think about is that this
is not a project that has been vetted by the Council or by the Community.
It is not on the CIP list like all of the other projects are. I don’t
believe Council has even reviewed the feasibility study. No agreements
have been reached about where the ferry would land in the Homer
Harbor. So, this might be a
great project but it would be kind of a leap of faith to include it given
our current lack of information and public input.
- College
Expansion: I spoke with Carol Swartz last week about the College’s
plans. As you may know, the College has decided to move forward to Plan B
and seek funding for approximately $8 Million to build a new building on
their existing property next to City Hall. If funding can be secured, I
understand that the College would no longer be interested in acquiring
City Hall, at least for the foreseeable future. Carol expressed an
interest in having this project included on the Council list. I told her
that she should submit a project description and that the Council would
consider it. Again, this project is a little different in that it is not
currently included on the CIP List.
- Voc-Ed
Center: This idea
was mentioned by Council member Zak at the last meeting. It is a very good
idea and I suspect there is a real need for that here. However, it is
really hard for me to see how we could possibly get the need and
feasibility studies and design and permitting done within 6 months. If
this was new construction, we would have to identify a piece of land. If
the idea is to refurbish the old school, we would have to have a better
idea of what was happening with the University. Perhaps it would be a good
idea to just seek money to upgrade the old school.
Recommended Water/Sewer Projects
- Homer
Water Storage/Distribution improvements Project: This project consists
of construction a 1.0 MG water storage tank, extending water main from East
Hill Road to Anderson
Street, and the abandonment of the existing
“A” Frame tank. We recommend that
an application be made for economic stimulation loan funds. This project is on the CIP list and
would allow the transmission mains and the water treatment plant to
operate at an average daily flow, improve fire flows, and improve
distribution system efficiencies. The HAWSP fund has limited ability to
fund new infrastructure projects. If
the loan does not have significant “forgiveness” provisions, we would
recommend that the offered funding be rejected. Total Cost = $3,900,000 ($390,000
design; $3,510,000 construction).
Schedule: Design – Mar 2009 to Dec 2009; Construction – Apr 2010 to
Oct 2010.
- Homer
Sewer Plant Bio-Solids Treatment Improvement Project: This project
consists of constructing an addition to the sewer plant and installing
mechanical sludge dewatering equipment, installation of a digester and
energy recovery system, abandoning the existing sludge lagoon, and
converting the lagoon to a flow equalization pond. We
recommend that an application be made for economic stimulation loan funds. This project is on the CIP list and
would allow for more effective sludge treatment, provide energy recovery,
storage of peak wet weather flows until they can be treated without
violating the plant’s NPDES permit, and create space for a future new
Public Works Complex. The HAWSP fund has limited ability to fund new
infrastructure projects. If the loan
does not have significant “forgiveness” provisions, we would recommend
that the offered funding be rejected.
Total Cost = $5,245,000 ($525,000 design; $4,720,000 construction).
Schedule: Design – Mar 2009 to Dec 2009; Construction – Apr 2010 to Oct
2010.
- Homer
Sanitary Sewer Rehabilitation Project:
This project consists of identifying sewer mains with potential
infiltration and structural integrity problems and slip-lining them to
correct deficiencies and eliminate infiltration. The main focus will be
the Ocean Drive sewer
main (highly corrosive wastewater) and the West Trunk; especially areas
with brittle asbestos cement (AC) pipe. The Bay
Avenue sewer lift station wet well will be
replaced. We recommend that an application be made for economic stimulation
loan funds. This project will
return structural integrity to the badly corroded Ocean
Drive main (receiving aggressive wastewater
from the Spit), reduce infiltration, and improve lift station
capabilities. The Water/Sewer Reserve Account has limited ability to fund
infrastructure improvement projects. If
the loan does not have significant “forgiveness” provisions, we would
recommend that the offered funding be rejected. Total Cost = $1,200,000 ($120,000
design; $980,000 construction). Schedule: Design – Mar 2009 to Apr 2009;
Construction – Jun 2009 to Nov 2009.
- Homer
Pressure Reducing Vault Replacement Project: This project consists of replacing four
existing PRV vaults (Ben Walters, Lucky
Shot, Lake, and A-Frame) that are in need of replacement. The City has recently replaced two of
the most needed replacements; this project would replace the other PRV
stations that are in poor condition. We
recommend that an application be made for economic stimulation loan funds. The Water/Sewer Reserve Account has
limited ability to fund infrastructure improvement projects. If the loan does not have significant
“forgiveness” provisions, we would recommend that the offered funding be
rejected. Total Cost = $600,000
($60,000 design; $540,000 construction). Schedule: Design – Mar 2009 to Apr
2009; Construction – Jun 2009 to Nov 2009.