MEMORANDUM #09-82

 

To:                   Walt Wrede, City Manager

From:               Carey Meyer, Public Works Director

Date:               June 5, 2009

Subject:          Midhill PRV Station Stairway - Contract Award Recommendations


Public Works opened bids for the above referenced project on June 5.  Three bids were received.

 

Bidder                                                     Location                  Base Bid

Twin Peaks Construction, Inc.                        Anchor Point, AK       $ 337,620

Jay Brant General Contractors, LLC              Homer, AK                 $ 235,733

Steiner’s North Star Construction, Inc.      Homer, AK                $ 175,927

Engineer’s Construction Estimate                                                      $160,260        

 

The apparent low bidder is Steiner’s North Star Construction, Inc., Homer, AK.  This project was not bid with the City’s 5% local bidder’s preference requirements (because of the use of state loan funds do not allow for local preference considerations).  The low bid is higher than the engineer’s estimate by 9%. The budget approved by the City Council is $190,000, including design and construction. The low bid received is within the project budget:

 

Engineering                             $     5,000

Construction                           $ 175,927

Administration                        $     3,000

Advertisement                                    $        900

Total Est. Project Cost            $ 184,827

 

Funding for this project is being provided by economic stimulus funding.  Public Works has indicated in the past that our understanding is that this funding is in a form of a forgivable loan.  The latest information from the funding agency (ADEC) is that “green” projects will be eligible for 100% forgiveness.  This project is now considered to not be “green” and may very well be eligible for only 90% loan forgiveness.  Public Works will engage the City council at the next meeting to formally establish funding for the 10% unforgivable portion of this project.  The unforgivable loan portion of this project is estimated to not exceed $19,000; Public Works will suggest that this portion of the project funding come from the Public Works Reserve Fund or HAWSP.

 

Recommendation:  The City Council award the construction contract for this project to Steiner’s North Star Construction, Inc., Homer, AK for the base bid amount of $175,927 and authorize the City Manager to execute all appropriate documents.                                           (Fiscal Note:  215-867)