CITY OF HOMER

PUBLIC WORKS                                                       TELEPHONE (907)235-3170

3575 HEATH STREET        HOMER, AK 99603                                 FACSIMILE   (907)235-3145

                                                                               

 

 

MEMORANDUM 09-96

 

To:                   Walt Wrede, City Manager

From:               Carey Meyer, Public Works Director

Date:               July 21, 2009

Subject:          City Hall Emergency Generator Installation

                        Construction Contract Award Recommendations


Public Works opened bids for the above referenced project on June 21.  Three bids were received.

 

            Bidder                                                Office Location              Bid

                                                           

Statewide Commercial Electric                      Anchorage, AK           $  34,250

Puffin Electric                                                 Homer, AK                 $  31,427

Steiner’s North Star Construction               Homer, AK                $  23,000 (apparent low bidder)

           

Engineer’s Estimate                                                                            $  28,500        

 

Public Works has reviewed the bids. The low bidder is Steiner’s North Star Construction, Homer, AK.  The low bidder’s qualifications have been reviewed and they have been determined to be qualified to complete this project.  This project was bid with the City’s 5% local bidders preference requirements.  The low bidder is a local bidder (office within City limits).

 

The project budget approved by the City Council is $69,000.  The low bid received will put total project cost within the project budget:

 

Engineering                 $   9,075

Purchase Generator     $ 28,189

Installation                  $ 23,000

Inspection                   $   2,600

 

Total Project Cost       $ 62,864

 

Recommendation:  The City Council award the construction contract for this project to Steiner’s North Star Construction of Homer, AK in the amount of $23,000 and authorize the City Manager to execute all appropriate documents.    

 

(Fiscal Note:  100-140-5901)