To: Walt Wrede, City Manager
From: Carey Meyer, Public Works Director
Date: July 31, 2009
Subject: HERC Boiler Installation
Construction Contract
Award Recommendations
Public Works opened bids for the above referenced project on July 30. Three bids were received:
Bidder Office Location Bid
Peninsula Plumbing & Heating Soldotna AK $ 39,500
Steiner’s North Star Construction Homer, AK $ 32,970
Sunland Development (Glen’s Mechanical) Homer, AK $ 26,900
Engineer’s Estimate $ 30,000
Public Works has reviewed the bids. The low bidder is Glen’s Mechanical of Homer, Alaska. The low bidder’s qualifications have been reviewed and they have been determined to be qualified to complete this project. This project was bid with the City’s 5% local bidders preference requirements. The low bidder is a local bidder (office within City limits).
The project budget approved by the City Council is $64,000. The low bid received will put total project cost within the project budget:
Engineering and
inspection $16,000
Single Boiler
Installation: $26,900
Boiler Purchase: $12,096
Contingency (10%): $ 6,000
Total Anticipated
Project Cost - $61,000
Recommendation: The City Council award the construction contract for this project to Glen’s Mechanical, Homer, Alaska in the amount of $26,900 and authorize the City Manager to execute all appropriate documents.
(Fiscal Note: 100-140)