A RESOLUTION OF THE CITY COUNCIL OF HOMER, ALASKA AWARDING THE CONTRACT FOR THE KACHEMAK DRIVE PHASE ONE WATER AND SEWER PROJECT TO THE FIRM OF HERNDON CONSTRUCTION LLC. OF HOMER, ALASKA IN THE AMOUNT OF $967,669.00 AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE APPROPRIATE DOCUMENTS.
WHEREAS, The Invitation to Bid was advertised in the Homer News on June 22 and 29, 2006,
Anchorage Daily News on June 25, 2006, Peninsula Clarion on June 25, 2006, sent to plans
rooms and posted on the City Clerk's Project Internet Web Site; and
WHEREAS, Sealed bids were due by 2:00 p.m. on Thursday, July 20, 2006 and two sealed bids
were received by the City Clerk's Office; and
WHEREAS, A Mandatory Pre Bid Conference was held on July 11, 2006 at 9 a.m.; and
WHEREAS, The bids were more than 15% higher than the engineer's estimate; and
WHEREAS, City Administration determined that the most appropriate and most expeditious
way to handle this was to rebid the boring work by substituting open trench road crossings; and
WHEREAS, The two bidders submitted sealed bids to Public Works which were due August 9,
2006; and
WHEREAS, Herndon Construction, LLC, of Homer, Alaska submitted the overall lowest
responsive and responsible bid in the amount of $ 967,769.00; and
WHEREAS, This award is not final until notice is received by Herndon Construction, LLC of
Homer, Alaska from the City of Homer.
NOW, THEREFORE, BE IT RESOLVED that the City Council of Homer, Alaska hereby
awards the Contract for the Kachemak Drive Phase I Water and Sewer Project to the firm of
Herndon Construction, LLC of Homer, Alaska in the amount of $967,769.00 and that the City
Manager is hereby authorized to execute the appropriate documents.
PASSED AND ADOPTED by the Homer City Council this 24th day of July, 2006.
CITY OF HOMER
________________________________
ATTEST: JAMES C. HORNADAY, MAYOR
MARY L. CALHOUN, CMC, CITY CLERK
Fiscal Note: Account Number: 215-826.