RESOLUTION 07-101(A)
A RESOLUTION OF THE
WHEREAS, The City Council selected Jay-Brant General Contractors as the GC/CM contractor, approving their design team (which included ECI/Hyer) as the most qualified; and
WHEREAS, The City has determined that a 10% conceptual design should be completed before continuing with final design; and
WHEREAS, Public Works has established a scope of work and schedule for ECI/Hyer’s portion of the 10% conceptual design; and
WHEREAS, Public Works has reviewed and approved the cost of this work, determining that a reasonable cost for this work is $101,980.00; and
WHEREAS,
This award is not final until notice is received by ECI/Hyer of
PASSED
_____________________________
JAMES C. HORNADAY, MAYOR
ATTEST:
______________________________
JO JOHNSON,
Fiscal Note: Account Number: