HOMER,
Public Works
RESOLUTION 08-12
A RESOLUTION OF THE
WHEREAS, The City Council awarded the GC/CM contract to Jay-Brant General Contractors, approving their design team (including Seabright Survey) as the most qualified; and
WHEREAS, The City has determined that a geotechnical investigation should be completed as part of the 35% schematic design; and
WHEREAS, The firm Seabright Survey has completed their portion of the 10% design for the New City Hall/Town Square project, and has uniquely qualified staff to complete the geotechnical investigation; and
WHEREAS, Public Works has established a scope of work and schedule for the geotechnical investigation, and has reviewed and approved the cost of this work, determining that a reasonable cost for this work is $23,500.00; and
WHEREAS,
This award is not final until notice is received by Seabright
Survey of Homer,
PASSED
_____________________________
JAMES C. HORNADAY, MAYOR
ATTEST:
______________________________
JO JOHNSON,
Fiscal Note: Account Number: 170-733-5212.