RESOLUTION 09-05


A RESOLUTION OF THE CITY COUNCIL OF HOMER, ALASKA, AWARDING THE CONTRACT FOR THE HOMER AIRPORT TERMINAL TILE INSTALLATION PROJECT TO THE FIRM OF STEINER’S NORTH STAR CONSTRUCTION OF HOMER, ALASKA, IN THE AMOUNT OF $48,458.00 AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE APPROPRIATE DOCUMENTS.

            WHEREAS, The Invitation to Bid was advertised in the Homer News November 20 and 27, 2008 and the Peninsula Clarion on November 23, 2008, sent to two in-state plans rooms, and posted on the Clerk’s website; and

            WHEREAS, Sealed bids were due in the Office of the City Clerk by 2:00 p.m. on Thursday, December 18, 2008; and

            WHEREAS, Four sealed bids were received and Steiner’s North Star Construction of Homer, Alaska, submitted the lowest responsive and responsible bid for the Airport Terminal Tile Installation Project; and

            WHEREAS, This award is not final until written notification is received by Steiner’s North Star Construction of Homer, Alaska, from the City of Homer.

            NOW, THEREFORE, BE IT RESOLVED that the City Council of Homer, Alaska, awards the contract for the Homer Airport Terminal Tile Installation project to the firm of Steiner’s North Star Construction of Homer, Alaska, in the amount of $48,458.00 and authorizes the City Manager to execute the appropriate documents.

            PASSED AND ADOPTED by the Homer City Council this 12th day of January, 2009.

                                                                        CITY OF HOMER

                                                                        ______________________________________

                                                                        DENNIS NOVAK, MAYOR PRO TEMPORE

 

ATTEST:

 

______________________________

JO JOHNSON, CMC, CITY CLERK

 

Fiscal Note: Funding budgeted in 2007 Airport Reserves $25,000 and 2008 Airport Reserves $45,000 Acct. No. 156-388.