CITY OF HOMER

HOMER, ALASKA

                                                                                                             City Manager

RESOLUTION 09-78

 

A RESOLUTION OF THE CITY COUNCIL OF HOMER, ALASKA, AWARDING THE CITY HALL EMERGENCY GENERATOR INSTALLATION CONSTRUCTION CONTRACT PROJECT TO THE FIRM OF STEINER’S NORTH STAR CONSTRUCTION OF HOMER, ALASKA, IN THE AMOUNT OF $23,000.00 AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE APPROPRIATE DOCUMENTS.

 

            WHEREAS, The City recently issued an Invitation to Bid for the City Hall Emergency Generator Installation Project; and

 

            WHEREAS, The Invitation to Bid was published in accordance with the City Code and appeared in the Peninsula Clarion on July 5, 2009 and the Homer Tribune on July 1 and 8, 2009; and  

 

            WHEREAS, Bids were due in the Office of the City Clerk on July 21, 2009 and there were three bids received; and

 

WHEREAS, The lowest responsible, responsive Bidder is Steiner’s North Star Construction of Homer, Alaska, in the amount of $23,000.00; and

 

WHEREAS, This award is not final until notice is received by Steiner’s North Star Construction of Homer, Alaska.

 

NOW, THEREFORE, BE IT RESOLVED that the City Council of Homer, Alaska, hereby awards the contract for the City Hall Emergency Generator Installation Construction Contract Project to the Firm of Steiner’s North Star Construction of Homer, Alaska, in the Amount of $23,000.00 and authorizes the City Manager to execute the appropriate documents.

 

PASSED AND ADOPTED by the Homer City Council this 27th day of July, 2009.



CITY OF HOMER



______________________________

JAMES C. HORNADAY, MAYOR

ATTEST:

______________________________

JO JOHNSON, CMC, CITY CLERK

 

Fiscal Note: $23,000.00 Acct. No. 100-140-5901