HOMER,
City Manager
RESOLUTION 09-78
A
RESOLUTION OF THE
WHEREAS, The City recently issued an Invitation to Bid for the City Hall Emergency Generator Installation Project; and
WHEREAS, The Invitation to Bid was published in accordance with the City Code and appeared in the Peninsula Clarion on July 5, 2009 and the Homer Tribune on July 1 and 8, 2009; and
WHEREAS, Bids were due in the Office of the City Clerk on July 21, 2009 and there were three bids received; and
WHEREAS, The lowest responsible, responsive Bidder is Steiner’s North Star Construction of Homer, Alaska, in the amount of $23,000.00; and
WHEREAS, This award is not final until notice is received by Steiner’s North Star Construction of Homer, Alaska.
NOW, THEREFORE, BE IT RESOLVED that the City Council of Homer, Alaska, hereby awards the contract for the City Hall Emergency Generator Installation Construction Contract Project to the Firm of Steiner’s North Star Construction of Homer, Alaska, in the Amount of $23,000.00 and authorizes the City Manager to execute the appropriate documents.
PASSED AND ADOPTED by the Homer City Council this 27th day of July, 2009.
CITY OF HOMER
______________________________
JAMES C. HORNADAY, MAYOR
ATTEST:
______________________________
JO JOHNSON, CMC, CITY CLERK
Fiscal Note: $23,000.00 Acct. No. 100-140-5901