Memorandum 19-006 Spit Fish Grinder Lift Station Renovation
Memorandum ID:
19-006
Memorandum Status:
Backup
Related Meetings
Related Ordinances/Resolutions
Details
Memorandum 19-006
TO: Katie Koester, City Manager
FROM: Carey S. Meyer, Public Works Director
DATE: January 8, 2019
SUBJECT: Spit Fish Grinder Renovation
The annual inspection of the Spit Fish Grinder Lift Station by Public Works, at the end of 2018, reveled significant corrosion of the pumps and pump rails. The rails need to be replaced and pumps need to be rebuilt.
This fish grinding lift station is located adjacent to the Fish Grinding Building on Fish Dock Road. All sport caught fish carcasses collected from around the small boat harbor (in the summer) and fish waste from fish processers (during the fish processing season) are ground up in the Fish Grinding Building. The lift station then pumps all fish waste to the Bay.
Public Works estimates the cost of rehabilitation the fish grinding station as follows:
Pump rebuild parts (lowest of three quotes)$ 16,525
Rail Replacement Materials$360
Shipping $1,500
Labor (190 hrs x $60/hour)$ 11,400
Subtotal$ 29,785
Contingency (5%)$ 1,490
Total Estimated Project Cost$ 31,275
Public Works water/sewer personnel will complete all work. All costs will be charge to the Port/Harbor Enterprise Fund.
Recommendation: The City Council amend the 2019 capital budget to create a Spit Fish Grinder Rehabilitation project, and authorize the expenditure of $31,275 from the Harbor Reserve Fund to complete the rehabilitation.