Resolution 15-014 Contract Award for Construction of Homer Small Boat Harbor Launch Ramp Renovation to Harris Sand & Gravel
Summary
A Resolution of the Homer City Council Awarding the Contract for the Construction of the Homer Small Boat Harbor Launch Ramp Renovation to the Firm of Harris Sand & Gravel of Valdez, Alaska, in the Amount of $3,412,000 and Authorizing the City Manager to Execute the Appropriate Documents. City Manager/Public Works Director.
Ordinance/Resolution ID:
15-014
Ordinance/Resolution Status:
Adopted
Effective Date:
03/09/2015
Related Meetings
Related Memorandums
Details
CITY OF HOMER
HOMER, ALASKA
City Manager/
Public Works Director
RESOLUTION 15-014
A RESOLUTION OF THE HOMER CITY COUNCIL AWARDING THE CONTRACT FOR THE CONSTRUCTION OF THE HOMER SMALL BOAT HARBOR LAUNCH RAMP RENOVATION TO THE FIRM OF HARRIS SAND & GRAVEL OF VALDEZ, ALASKA, IN THE AMOUNT OF $3,412,000 AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE APPROPRIATE DOCUMENTS.
WHEREAS, Competitive bids were solicited for the construction of the Homer Small Boat Harbor Launch Ramp Renovation project by ADF&G in conformance with their procurement policies; and
WHEREAS, Five bids were received February 20, 2015 (see Memorandum 15-029); and
WHEREAS, Harris Sand and Gravel of Valdez, Alaska, was found to be the lowest responsive bidder; and
WHEREAS, ADF&G is responsible for designing and bidding the project, but the City of Homer is responsible for issuing and administering the construction contract; and
WHEREAS, This award is not final until written notification is received by the firm from the City of Homer.
NOW, THEREFORE, BE IT RESOLVED that the City Council of Homer, Alaska, approves the construction contract award for the completion of the Homer Small Boat Harbor Launch Ramp Renovation project to the firm of Harris Sand and Gravel of Valdez, Alaska, in the amount of $3,412,000 and authorizes the City Manager to execute the appropriate documents.
PASSED AND ADOPTED by the Homer City Council this 9th day of March, 2015.
CITY OF HOMER
________________________
MARY E. WYTHE, MAYOR
ATTEST:
___________________________
JO JOHNSON, MMC, CITY CLERK
Fiscal Note: 456-0921