About Homer
-
- Americans with Disabilities Act Compliance Program City Campgrounds Community Recreation Hickerson Memorial Cemetery
- Library Parks & Trails Public Safety Fire Police Emergency Information
- Events & Activities City Calendar Library Calendar Recreation Calendar Doing Business in Homer Sister City Program Coast Guard City
-
- Departments
- Government
- How Do I?
Resolution 17-001 Final Cost for the Shellfish Avenue/South Slope Drive Water Main/PRV Project
Summary
A Resolution of the Homer City Council Establishing the Final Cost for the Shellfish Avenue/South Slope Drive Water Main/PRV Project to be $590,314 and the Per Lot Fair Share as $11,292. City Manager/Public Works Director.
Ordinance/Resolution ID:
17-001
Ordinance/Resolution Status:
Adopted
Introduction Date:
01/09/2017
Effective Date:
01/09/2017
Related Meetings
Related Memorandums
Details
CITY OF HOMER
HOMER, ALASKA
City Manager/
Public Works Director
RESOLUTION 17-001
A RESOLUTION OF THE HOMER CITY COUNCIL ESTABLISHING THE FINAL COST FOR THE SHELLFISH AVENUE/SOUTH SLOPE DRIVE WATER MAIN/PRV PROJECT TO BE $590,314 AND THE PER LOT FAIR SHARE AS $11,292.
WHEREAS, The construction of Shellfish Avenue/South Slope Drive Water Main and PRV project is complete and is ready for adjacent property owners to connect; and
WHEREAS, The City Council passed Resolution 16-078(S) establishing policy and the conditions under which adjacent benefitted property owners could connect to the new main (per Memorandum 16-120); and
WHEREAS, The policy included the need for the Council to approve the final costs of the project and the per lot “fair share” that property owners would be responsible for; and
WHEREAS, Public Works has determined the final cost of the project to be $590,314, determined the portion of the project cost covered by grants, and calculated the per lot share as documented in Memorandum 17-010.
NOW, THEREFORE, BE IT RESOLVED that the City Council of Homer, Alaska, establishes the final cost of the project to be $590,314 and the per lot share to be $11,292 for the Shellfish Avenue/South Slope Drive Water Main/PRV project.
PASSED AND ADOPTED by the Homer City Council this 9th day of January, 2017.
CITY OF HOMER
________________________________
BRYAN ZAK, MAYOR
ATTEST:
______________________________
JO JOHNSON, MMC, CITY CLERK
Fiscal Note: Project cost $590,314; property owner per lot share $11,292.