Memorandum 18-024 Frisbee Court Paving SAD Final Assessment Recommendations

Memorandum ID: 
18-024
Memorandum Status: 
Backup

Related Meetings

Details

MEMORANDUM 18-024

 

TO:                        Mary K. Koester, City Manager

FROM:                 Carey Meyer, Public Works Director

DATE:                   February 16, 2018

SUBJECT:          Frisbee Court Paving SAD Final Assessment Recommendations

The City Council authorized the creation of a road paving special assessment district for the above referenced subdivision by passing Resolution 17-017. Public Work coordinated the design and construction of these improvements, and construction was completed in September 2017.

Project Costs:

Design/Inspection - Nelson Engineering          $       14,523.00
Construction - East Road Services                     $     156,334.63
PW Review/Inspection/Management Labor     $         4,184.30

Total Expenditures                                               $     175,041.93

5% Finance Overhead                                          $         8,752.10

Total Project Cost                                                  $     183,794.03

 

25% of the cost of the road improvements are the responsibility of the benefited lot owners.

$183,797.18 x .25 = $45,948.51             

$45,948.51/11 Lots = $4,177.14/ lot

 

Recommendations:

The City Council pass a resolution confirming the assessment roll, and establishing dates and conditions for assessment payment for the Frisbee Court Road Paving Special Assessment District.