Frisbee Court Road Paving Improvements Pre Bid Conference

Calendar Date:
Tuesday, June 27, 2017 - 1:30pm

A Pre-Bid Conference will be held at 1:30 p.m. on Tuesday, June 27, 2017 in the City Hall Second Floor Conference Room (491 East Pioneer Avenue) to answer bidder’s questions. Immediately after, interested parties can complete a site visit with the City Engineer.

This project is funded through the City of Homer Accelerated Roads/ Trails Fund (HART). The City’s local bidder’s preference requirements do apply to this contract; State prevailing wage rates will apply.  The work includes, but is not limited to the following:

 Construction of 400 LF of road improvements including excavation, import of classified fill, paving, signage and striping.